Port of Devonport - Interim Berth Works

The Port of Devonport is a major Tasmanian cargo port and a key gateway for tourists and locals. Each year ~400,000 passengers and ~4 million tonnes of freight transit the port. It’s also the home of TT-Line’s Spirit of Tasmania, as well as SeaRoad.

QuayLink is TasPorts’ largest project in a generation and the largest port upgrade project under the Port Master Plan. It is designed to modernise and future-proof the port, enhancing technology, safety and operational outcomes for customers.

QuayLink includes a number of work packages, some of which are being delivered by TasPorts, while others are delivered by port customers, including TT-line and SeaRoad.

Devonport Port layout

TasPorts’ work package included the delivery of a new berth pocket, wharf structure and reclamation area at the existing Berth 3E, specifically designed for the new Spirit of Tasmania vessels, which was completed on 8 July 2024, on time and on budget.

In June 2024 the Tasmanian Government directed TasPorts to assist TT Line by undertaking an upgrade of Berths 1 and 2 to ensure contingency infrastructure was in place for the arrival of the new vessels, while TT-Line delivers its Berth 3 works.

TasPorts responded immediately by establishing a dedicated project team, to ensure the appropriate support and expertise to deliver on the necessary infrastructure. It also implemented strong governance and extended the gateway review process already in place for TasPorts’ QuayLink project, as a critical assurance mechanism to effectively and transparently support the project delivery.

TasPorts understands the critical importance of the Spirit of Tasmania vessels to Tasmanians and the Tasmanian economy, and is targeting the earliest possible date for the completion of this work.

Frequently Asked Questions

TasPorts is working to adapt Berth 1 to accommodate the new vessel.

Engineering consultants have been engaged, with engineering assessments underway. Materials required are being identified and incorporated into the schedule.

TasPorts is working with TT-Line and SeaRoad on all opportunities to minimise disruption and optimise capacity.

We have prioritised this project and we are targeting the earliest possible date. To be clear, we are talking months, not years. The design work, together with sourcing of materials and securing of contractors will assist to determine the exact timeframe. Once known, this will be communicated to stakeholders as a priority.

The Berth 1 ramp was originally built in 1974, and while fit for the current TT-Line vessels, modifications will be needed to accommodate the new vessels. This means a section of the ramp needs to be extended and due to the extra weight, modifications to the ramp lifting arrangements will be required. This may include upgraded winch motors, wire rope, sheaves and brakes.

The new ships being bigger also have specific berthing requirements. This means we need to install new fenders and bollards. Given the depth (draft) of the new vessels, they will also need to have restricted load carrying capacity while at Berth 1, and in line with their length, we will need to install additional bollards to ensure they can be safely secured in high winds.

The works being undertaken will need to be carefully managed to ensure Berth 1 can accommodate the new vessel, as well as continue to accommodate the existing Spirit vessels.

TasPorts has looked across its other ports, however they all have similar challenges to Berth 1 at Devonport.

The design works, sourcing of materials and resources will determine the final costings for the interim solution.

TasPorts is working closely with its shareholders, the Tasmanian Government, on funding strategies.

TasPorts will continue work with its port partners including SeaRoad, to deliver the contingency infrastructure upgrades in a timely way to support all its customers.

Although there is an existing direction from Government to TasPorts that the Berth 1 works are to proceed should a viable option exist, TasPorts will be presenting its proposal for the Berth 1 upgrade works to TT-Line and Government in mid-October for confirmation that proceeding with the proposal is supported.

For further questions please contact communications@tasports.com.au