Burnie Berth 4 Remediation Works

Essential wharf remediation works are underway at Berth 4 in the Port of Burnie supporting Tasmania’s leading freight gateway. 

The 16-month program of works, will remediate, strengthen and future proof this critical asset against scour and erosion for decades to come. 

TasPorts continues to work closely with Strait Link, and all port customers, to ensure the project results in limited impact to freight movements with all works delivered around shipping schedules. 

Works will be delivered from April 2026 with practical completion expected for June 2027.  

News and Updates

Read recent news and media releases on the Burnie Ground Improvement Works 

Media Releases

Project News

Sign up for project news or submit your question at 

BurnieBerth4project@tasports.com.au 

 

Frequently Asked Questions

TasPorts is delivering essential wharf remediation works to incrementally strengthen the ageing wharf structure. These works are necessary to ensure the long-term resilience and efficiency of port operations.  

Three remediation techniques will be used, including:

  • Ground improvement works behind the concrete wharf to further strengthen the entire quay wall and wharf structure at Berth 4.
  • Scour protection of wharf infrastructure to be installed below the water surface and at the toe of the quay wall.  
  • Installation of high-capacity grouted steel micro-piles through the existing wharf structure. 

TasPorts has awarded a local construction company BridgePro Engineering, alongside specialist sub-contractor Wagstaff, a contract to deliver a 16-month program of remediation works at Berth 4. 

The remediation works will be delivered across a 16-month program from April 2026.  

The project is on track for practical completion in June 2027.  

Regular updates will be shared on our website. Questions and feedback can also be directed to BurnieBerth4Project@tasports.com.au